The fire damaged container was an old internal office, all the charred timber and panelling needed to be pulled out using the tractor, there was a lot to do.
The old roof felt removed left several holes, plates welded to give roof integrity, roof vent shafts fabricated from 1mm steel plate were welded into 3 positions, these vent shafts would have flaps to allow metering of air flow
The patches and roof vents fully fitted / painted soon the roofing felt was bonded to position folded on the edges glued. This job of roofing gave more insulative property to the convective heat loss, prevented corrosion to the building making weather proof !! September 2022
Fabrication of ducts for the lower input air, it is thought convection of flowed air will work sufficiently and effectively without using forced air flow although if a plan to filter the air was in place then it would likely require some fans powered by electricity to keep the environments moving within the early life living areas up to 10 days
It was decided for safety reasons that a personel door should be made and installed October 2022
This new door would allow access to part of the building that would be Incubation only
|